Construction
Permit Application Process
Important
first steps:
1. Confirm your planned construction is within established set-back
limits. If you are unsure of the set-back limits for the Zone
your property is in, check with the Livingston Zoning Office.
You may be asked to submit a Zoning Review form.
2.
Bring a copy of a survey of your property to the Zoning Office
on your first visit. Draw your planned construction on a copy
of a property survey for review with the Zoning Office. Ensure
the drawing is to scale and complies with all zoning and set-back
rules.
3.
A Permit Request Form and Construction Permit Application (page
1, page 2, page
3) is required for all construction listed below.
There are some categories of construction that do not require
this form. For both Major and Alterations categories below, the
Electrical and Plumbing sections of the Permit Request Form should
be filled out by a licensed Electrician and Plumber, who must
also place their seal on the form. You will receive these forms
on your first visit to the Building Office to review your planned
construction.
4.
Major categories below also require a Development
Fee Calculation Form. Print out the form, fill it
out, make 5 copies and bring in with your Permit Application.
5.
When submitting your Construction Permit Application, provide
three (3) sets of construction drawings and a sealed survey of
the property certified to current owners. Also, a copy of the
sealed survey showing the proposed work drawn to scale if the
footprint or height of the home is changing.
|
|
|
New
Homes*
|
Basement
Kitchen
Bathroom
(need riser diagram)
A/C,
Furnace
Deck
Cabana*
Pool,
Tennis Court*
Shed
(100 square feet or more)
|
Roof
Permit - $85.00
Siding
Permit - $85.00
Roofing
& Siding Permit - $170.00
Oil
Tank Permit - $100
|
*Requires
Development Fee
Calculation Form
**May need development fee. To be determined upon review
of each project individually.